§ 33-277. Bidding for installation of extension lines; approval of construction costs.  


Latest version.
  • (a)

    The selection of a Contractor for the installation of the extension water or sewer line shall be made by competitive bidding. in accordance with A.R.S. Title 34 and any and all applicable provisions of Article 2 of the City Code. The Developer shall submit to the City a notarized copy of all bids received, a copy of the bid tabulation and any information concerning the successful bidder. Both the City and the Developer shall have the right to reject any and all bids. No contract shall be awarded for installation of an extension water or sewer line prior to City approval of the successful bidder.

    (b)

    After the Contractor has been selected and approved by the City to perform the extension installation work, the Developer shall submit the total proposed construction costs for the installation plus the projected engineering costs to the City. No construction may commence prior to the City's approval of these costs.

(Ord. No. 3003, § 1(Exh. A), 9-27-16)